Wednesday 31 December 2014

A day in the life...

We had one plastered ceiling left, in a bedroom, that I had earlier decided would be too much hassle to rip down. Yesterday, however, I changed my mind, and set a challenge to get the plaster down and to get the beams underneath cleaned, and ready for new plaster between them. Having been out the night before with the volunteer fire fighters, it wasn't the easiest task to start with, but ten hours later, it was done. Making a few short films during the day, the result is a summary of the whole task.

Ripping down such a ceiling, with all the dirt hiding above it, is quite easy, but very dirty. But the cleaning of the beams is physically quite demanding and hard on the arms and back, holding sanding machines overhead for considerable lengths of time. Not to mention what feels like half a sandpit in your eyes, despite protection!

We hope to have the plastering done next week, but in the meantime, there's still loads to do between laying floors, and most importantly, getting the bathroom finished!

My apologies for rambling in the first section, but my brain wasn't fully activated... :)




Monday 22 December 2014

More floors and more tiles

We're so focused on getting stuff done, not to mention my wife is also working a lot over the holidays, that we've missed the window for sending Christmas cards! So with that in mind, less text, and more video. Click here for the big version, and not that little postage stamp below.



Tuesday 9 December 2014

First oak floors down - video update

Either I'm getting lazy, or I simply don't have time. I'm going for the latter. Another video-only update, where you can see some major progress with one of the bedrooms, and the first bits of oak flooring having been laid.


Monday 24 November 2014

Grain store fully converted

I didn't get time to write a nice blogpost with photos yesterday, and now I'm on an enforced break from construction as I travel for business for a couple of days. So video only!

Main points:
Our bedroom (the one we've now decided to have upstairs, where the former grain store was) is now ready for decorating after a marathon few days and nights. And we have a shower tray!



Click here for the bigger version.

Thursday 20 November 2014

The kitchen has landed

It seems I've been a bit remiss with the updates, but I have a good excuse: burning the candle at both ends. Starting the day job shortly before 8am, popping over to the building site at around 4:30pm and, the last few nights, staying there till midnight with an hour break for supper with the family. But energy levels are high, and I'm getting a lot done up on the neglected second floor. But I'll come back to that in another post. This post is all about the kitchen. Major milestone alert!

On Monday last week, the people from wohnfitz came with the kitchen. They spent two days in the house, putting it together, and I have to say, I'm really pleased with both the kitchen, and the care they took fitting it. We made our initial order about two years ago! So this was a long time coming, and when I look back at two or three years with of photos from the same room, it's been an amazing transformation, if I do say so myself. Of course, all the stuff I did is now hidden!

And now, the gallery.

Painting done after the synthetic resin screed was laid.
Tiled floor done!
And the kitchen is in...









There's still some detail work to do. We have to pick tiles for a splash back (we'll probably use the same model as the floor tiles, but smaller) and fit the lighting, but once we move in, we'll make it truly our own with other touches.

For a live view, you can also have a look at a bit of a walkthrough here from last weekend (including a quick look upstairs where it really is still a building site).


Sunday 2 November 2014

First spots of colour

Two weeks ago, I was bemoaning the fact we hadn't picked out colours. An intensive session a week ago resulted in colours being picked for the office, bedroom, kitchen and hallways, and a few days later both the office and kitchen were already painted.

Before my wife did that, I had to complete all the window sills, so they were sanded and varnished, three times, and set into place with expanding foam, and the gaps sealed with acrylic mastic for a tidy fit. A satin finish gives the oak a little sheen, in contrast with the matt, oiled ceiling beams.


In the office, we went for a natural, earthy tone. Or beige, depending onhow you see it. here's a before and after.




I'll be spending a lot of time sitting in this room, so I quite like the warmth.

In the kitchen we've been a bit braver, and have chosen two green tones. We wanted something to contrast with the cream/vanilla kitchen units, and to complement the floor tiles, which have bluey-green notes (well, the model name is "forest" after all), so green seemed to fit the bill. It might seem a little extreme now, but once the units are in, and some furniture and stuff on the wall, I think it'll give a nice fresh effect.


The bedroom is now ready to paint. I had to do some extra skimming here, as we changed our mind about cladding the installation shaft to look like the old chimney, given the price. We can always do that later if we have the cash and time.


The living room is also ready to paint, once we pick a colour here.


The two remaining areas on this floor that needed a lot of attention were the hallway and bathroom.

In the bathroom, three of the walls are ready for tiling/painting, but the remaining half-timbered wall is causing me some heartache. I almost regret leaving it visible, but we did it for the character itwould lend the room. However, it also happens to be the wall where the sink should be. We can't hang a sink or cabinet on the wall itself, as the clay plaster would not hold them,so we need another solution. We also need to decide on whether to simply use clay plaster, or put some mosaic tiles into the panels. Otherwise, we still have to pick out the shower base and toilet, so this room is the main showstopper for moving in before Christmas.



The problem wall
In the hall/stairwell, the walls on most sides were done, with only the old clay panels to replaster. I finally completed this over the weekend, so it feels a lot different already. But thre stairs themselves also needed attention. When we bought the house, the stringers were painted grey, the treads and risers were varnished quite dark, and the underside was clad with tongued and grooved pine boards. Here it was back in 2010.


My wife got the grey layer off with a delta sander, and yesterday, i took an orbital sander to it to try to get it down to the natural wood, which turned out to be beautiful oak. The tread also seem to be oak, while the risers are a paler, woodwormier softwood of some sort. In the shot below, the top steps are before an initial sanding. They all need more work, so that dusty work will get done this coming week.



And the shot below shows the final coats of paint being removed on the lower half of the stringer, revealing beautiful grain, not to mention the clay plaster job in the panels behind the stairs.


I have plans for the old metal banisters, to give them a new lease in life, but that can wait a few weeks, I think.

For those who need more, a short walkthrough from this morning.



So, progessing quite well. The next two weeks will see some huge changes. We have to get the kitchen floor tiles down in the next few days, as the kitchen comes in just over a week. Tomorrow I order our floorboards, so we'll have them delivered in about three weeks, so could start the flooring soon after. But I've got the second floor to partially complete before we can do that, as we need one more bedroom, as well as completing the stairwell, so we don't muck up the place later on.

Sometimes I'm not so sure we'll make it, but the will is there!

Sunday 19 October 2014

If only we could decide on colours...

Busy, busy, busy. Feels like we're burning the candle at both ends, but not seeing all that much for it. But then, we're seeing every day, so when someone comes and visits the site and tells us it looks like we could move in already, then it feels good. Of course it's nowhere near ready, but a lot closer than a few months ago.

All the walls on the first floor have been filled, skimmed, sanded and primed, so are ready for painting. All the clay ceilings have also been primed, and the kitchen, office and bedroom have been painted with an "old white" silicate-based paint, for maximum breathability, one of the advantages of clay that we'd like to preserve.

I've been motoring on with making the window sills, and have 13 of 30 nearly complete. All they need is a sanding, some edging done (when my new router arrives next week) and a sealing/finishing before fitting. Once that's done, we can start painting the walls. The hardest part is now deciding on a colour scheme! For most of the rooms this should be easy, but for the kitchen, we want something that contrasts with the units, complements the floor tiles (which have touches of green, blue-green, earthy brown etc), all while not being either too dark or cold-looking. It's not easy when your head is still full of many construction decisions to be made.

Upstairs still needs attention, as we've been concentrating on getting the first floor complete, but I hope to get started with the skimming and final drywall construction on most of the second floor in the next couple of weeks. At least to get the hall areas clean, and one bedroom. A second bedroom would be a bonus, but I need to complete some lighting wiring there.

And last, but not least, our Elektromeister friend Sace has continued connecting my wiring to the trip switches and installing presence sensors and the like, so we've got light throughout the cellars, making it much more homely.

Have a look at a bit of a walk-through showing the highlights from the past three weeks.


And the photos:









Sunday 28 September 2014

Let there be light

Milestone alert!



To see a video of this, have a look here. Yep! Pretty much a year after I laid the cables, and thanks to our Elektromeister friend, Sace Bakan, they are now hooked up doing their job. We now have a few working light and sockets, which makes a huge difference after three years having to bring an extension cable and light everywhere we went. It also feels like a working house, as we're getting near enough to the decorating stage.

Oiling of the beams on the second floor has continued, which certainly darkens, and livens the wood up.


In this shot, you can see the effect of the oil, as the base beam is partially oiled, and the diagonal on the right not yet oiled.


So we'll be getting some nice contrasts when the plastering and painting is done in this room.


Meanwhile, I've spend most of the past two weeks jointing, skimming and sanding, to get the final plaster surfaces ready for decorating. I skimmed the green boards in the kitchen yesterday, including the ceiling, and while it's far from perfect, a touch of sanding should do the trick.


Of course, the small details take time, like the transitions between old and new ceilings, which I did as simply as I could.

And of course, some more moulding and sanding needed, but it should look good once complete.


We also made a start on making the window sills, with the help of another friend, Werner, who has stuff like this brilliant table plane. I want one.


The sills are being made from glued laminated timber, so solid wood, but less risk of bowing or warping. My original idea of reusing some of the original solid oak floorboards as sills was a bit unrealisting, as they were not as straight as I thought.

We bought enough timber to make 24 sills, and the process is simple enough. We do some tricks to make it look thicker than the 18mm it has, by gluing a strip underneath. Once the basic shape has been cut and the fit checked, we'll round the edges with a router (slight rounding), then sand/polish them and oil them, with some final surface treatment to allow them to stand up to wear and tear.



And our tiles arrived just over a week ago, ahead of schedule. They'll stay in the barn for a few more weeks, till the kitchen ceiling and walls are decorated. Greener than we thought, but every tile is different, so it should be a nice effect.



And it's worth a video ;)


Monday 15 September 2014

Mid-September mini-update

Work isn't going fast enough for me, despite the fact that every free hour the past week has been on the building site. But we did take a short break for a few days the week before, to visit Legoland and be tourists before school starts again, but small things have been lying heavily on my mind.

Skim coating and filling has continued in the living room, "bedroom" and office, while dry walling has resumed, this time in the hall, which had been neglected for some time now.



The stairs got some tender loving care from my wife and a Fein Multimaster, so the old grey paint is gone, as is the ugly cladding that used to be on the underside.


And the old brick chimney in the kitchen got a facelift with some joint a l'ancienne to repoint it with some very attractive mortar. Here's a before and after.



Actually, that was quite a lot of before and after in one shot. Plastering, plasterboard, floor, ceiling...

And for the gluttons for punishment, here's a another walk-through with the highlights from the past two weeks.


Friday 12 September 2014

Kitchen is Coming

A phrase that strikes more fear into my heart than a winter in Westeros. Kitchen is coming. Week 46. Second week of November. This means a lot of things have to fall into place, at least in the kitchen, before then.

But let's take a look back. We actually got our original kitchen design done about two years ago. We naively thought we'd have it installed within six months, but that's pretty much a recurring theme with our renovation. SInce the plastering, plasterboards and underfloor were all done a few weeks ago, it was time to get WohnFitz (renamed from Schäfer & Fitz) back again to remeasure, and a few days later to revise the plans and make sure the equipment we ordered was still available.

As it turns out, the only thing that was no longer available was the double sink in farmhouse style, so we opted for a single basin, but with a draining board. We slightly shifted the island so there was more space between it ans the other kitchen units, and swapped around some presses with drawers.

I still regret not having an oven at chest level, but I'm happy with the overall layout. And given the wonderful 3D renderings from Frau Krieger, we can imagine how it might look quite well.





Yes, it could look like this!


So what has to be done? We ordered the floor tiles last weekend, so they should arrive from Italy in about a week. This is them.



Although there were paler versions of the same range available, we chose these to give a contrast with the vanilla tone of the kitchen units, so they work quite nicely together. We plan on laying them in about four weeks, so we've got that much time to sand down the filler/skim coats on the walls, paint the ceiling, connect the wiring and get the sockets running, apply whatever finish we decide on to the walls, and paint, if required. Not too much, actually, in the scheme of things.

My biggest issue is deciding on the wall finish. Either a roll-on plaster to give a slight structure to the finish (fine sandy grain), or just paint onto the skimmed walls. Then there's colours to choose. I could really do with tips from an interior designer to give some options, as my head is too full of construction details that need to be finished elsewhere.

Anyway. We're getting there, and the plan to move in before Christmas is still possible.

Friday 29 August 2014

Big leaps!

It's been a full-on couple of weeks since the last update. I had been continuing to install the plasterboard walls on the second floor, but when our friend Sace turned up with the panels for the kitchen floor heating, the focus switched completely to that.

Over most of a day, we put down a thin layer of expanded clay aggregate to level out the hollows left by my poor attempt at a liquid screed, followed by the panels you see below. Once these were down, five heating loops were laid.


We had intended to pour a liquid screed (pumped this time, not mixed by hand), but when we checked the levels, we has less than the 40-45mm clearance recommended by the manufacturer. I have to admit, the liquid screed was more or less a plan B, as we thought it'd be cheaper and we'd have enough height, but originally, we'd discussed a synthetic resin screed, which is what we fell back to. Sace made a few calls, and the next day someone came over to have a look and give us a quote. Three days later, they came a did it. The results were... spectacular.


The beauty of this system  is that it needs no drying out time. So the next day, it was ready to be tiled. Also, you can go fairly thin, down to 1cm or so (we had 3 to 4cm).

If feels so weird having a perfectly level surface to walk on in the kitchen, after about three years of something resembling the surface of the moon.

This of course took away the last large barrier to our kitchen plans. Long-term-readers may recall we ordered our kitchen over 2 years ago, so it was time to revisit that, check the equipment still existed, and make some minor changes. I'll come to that in another post (it's worth it).

But of course, everything else needs to be done before the kitchen install, not least the floor tiles. But before that, the walls and ceilings need to be complete. Right now, the beams are all oiled, and the clay plater has been treated with a silicate-based "primer". The plasterboard walls and ceilings have been jointed and filled, and I've tried my hand at skim-coating the rest of the walls, with fairly decent results.


The skim-coating and filling has also continued into the living room, and once all of this gets some slight sanding and some corners cleaned up, we're actually ready to start decorating!Well, that and the window sills need to go in first.


So, quite a lot of progress in the last three weeks, but the next couple of weeks will be mostly filling, skimming and sanding, I fear.

And for those who like a proper commentary, here's a short walk-through of the first floor as of today. Click here for a large version.